Comment

Alternative Sites Consultation

Representation ID: 44158

Received: 07/04/2010

Respondent: Environment Agency

Representation Summary:

The development of this site will require detailed FRA to illustrate how surface water run off will be controlled at green field rates. A holistic drainage design scheme must be developed to demonstrate that there will be no increase in surface water to the adjacent watercourse. As with all the sites SuDS must be utilised and none use fully justified.

Full text:

The development of this site will require detailed FRA to illustrate how surface water run off will be controlled at green field rates. A holistic drainage design scheme must be developed to demonstrate that there will be no increase in surface water to the adjacent watercourse. As with all the sites SuDS must be utilised and none use fully justified.