Object
Publication Draft
Representation ID: 66683
Received: 27/06/2014
Respondent: Save Warwick
Legally compliant? No
Sound? No
Duty to co-operate? Yes
Representation Summary:
The plans for the necessary social infrastructure are not ready. Assumptions are made in the Plan that schools, medical centres, hospital beds and other social infrastructure will be provided. We are currently aware that school issues have not been automatically agreed with the County Council. Similarly the successful conclusion of other facilities cannot be assumed.
There is a serious funding gap for necessary infrastructure. Work done by save Warwick indicates that there is a there is a shortfall between the cost of infrastructure and the funding available in the region of 50 million pounds.
Full text:
See attached