Object
Publication Draft
Representation ID: 66110
Received: 27/06/2014
Respondent: CALA Homes (mids) Ltd
Agent: Cerda Planning Ltd
Legally compliant? No
Sound? No
Duty to co-operate? No
Objections are raised to this policy, in particular to part (c). Restricting developments of 50 or more homes to phasing construction of a development over 5-years is contrary to the NPPF which seeks to make up the shortfall of housing immediately and to boost significantly the housing supply.It has no consideration to the practicalities of building out a site, the finances involved or the prolonged disturbance to existing residents.No evidence has been provided as to why this phasing is necessary in terms of social cohesion and no evidence is available to demonstrate that the impacts on viability have been considered.
See attachment