Draft Charging Schedule - Jan 2017

Search representations

Results for Gladman Developments search

New search New search

Object

Draft Charging Schedule - Jan 2017

Draft Charging Schedule - Jan 2017

Representation ID: 70352

Received: 20/02/2017

Respondent: Gladman Developments

Representation Summary:


It is understood that the Council have now refreshed the evidence base which underpins the charging schedule and this letter sets out Gladmans' response to both the charging schedule and its accompanying evidence base.
The Council states in paragraph 4.2 of the charging schedule that the Councils responses were reported, to the 2013 consultation, in January 2015. Gladman noted in our last representation that these responses did not take into the consideration the points made by Carter Jonas in the duly made representation from 2013. We note that we have still seen no record from the Council that these representations have been considered, nor have we seen any counter point to the evidence put forward by Carter Jonas.
Although each CIL charging schedule needs to be locally evidenced, to take account of local circumstances, the proposed rates for Warwick District (Zones B and D) are the highest currently proposed of any authority in the East or West Midlands1. Indeed authorities, which may be considered good comparisons, such as Stratford-on- Avon and Solihull have upper end residential charges of £150 p/sqm. Whilst high these are nearly 25% lower than those proposed for Zones B and D in Warwick.
We have previously cautioned against the potential for such large CIL rates to have a negative impact of 'market shock' upon Warwick District.
Charging Zones
Gladman maintain the view that the proposed boundaries for the Charging Zones are not robustly justified. Whilst we understand the broad premise for the Charging Zones, it is not clear how the District Council has arrived at the proposed boundaries. Furthermore the map which accompanies the charging schedule is unclear.
CIL Viability Report
Gladman have considered the tables set out in the BNP Paribas report on pages 33 and 34. It is noted that a number of development scenarios are offered. We retain a number of concerns with regard to the way in which the evidence base has assessed the viability assumptions that the CIL charges will have, particularly about the cumulative impact of the CIL rate in the higher zones with an affordable housing requirement of 40%.
Regulation 123 List
The Regulation 123 infrastructure list has not been published. The Council will need to publish this documentation for comment. Local planning authorities need to be able to demonstrate the infrastructure need and subsequent funding gap and must ensure that the level of total CIL receipts that could be generated through the levy reflects the true needs and proposals in the Local Plan
When establishing a funding gap that CIL receipts are intended to contribute towards filling, it is vital that the Council take account of every possible income stream.
The Council need to have an up to date, robust evidence base that fully justifies the infrastructure needs based on the amount of development that is required. Information on these infrastructure needs should, wherever possible, be drawn directly from the infrastructure planning that underpins the Development Plan, as this should identify the quantum and type of infrastructure required to realise their local development needs.



For instructions on how to use the system and make comments, please see our help guide.